Two of four headrace tunnels in the Jinping II hydropower project were constructed using tunnel boring machines (TMBs). The geology along the tunnel alignment is dominantly massive to highly fractured marble and the maximum overburden depth is 2,525 m. The paper discusses the problems encountered during the TBM tunneling, including instability of the tunnel wall and face induced by high in situ stresses, high-pressure groundwater inflows and excessive cutter and cutterhead damage. Measures taken to overcome these problems involved modifications to both the machines and the mode of operation as well as changes to the support parameters.

关键词:

In situ stress TBM optimization Tunnel boring machine (TBM) Groundwater inflow Marble

作者机构:

  • [ 1 ] [Gong, Q. M.]Beijing Univ Technol, Key Lab Urban Secur & Disaster Engn, Minist Educ, Beijing 100124, Peoples R China
  • [ 2 ] [She, Q. R.]Beijing Univ Technol, Key Lab Urban Secur & Disaster Engn, Minist Educ, Beijing 100124, Peoples R China
  • [ 3 ] [Yin, L. J.]Ecole Polytech Fed Lausanne, LMR, CH-1015 Lausanne, Switzerland

通讯作者信息:

  • 龚秋明

    [Gong, Q. M.]Beijing Univ Technol, Key Lab Urban Secur & Disaster Engn, Minist Educ, Beijing 100124, Peoples R China

电子邮件地址:

查看成果更多字段

相关关键词:

来源 :

BULLETIN OF ENGINEERING GEOLOGY AND THE ENVIRONMENT

ISSN: 1435-9529

年份: 2013

期: 2

卷: 72

页码: 163-172

4 . 2 0 0

JCR@2022

ESI学科: GEOSCIENCES;

JCR分区:3

中科院分区:4

被引次数:

WoS核心集被引频次: 29

SCOPUS被引频次: 31

ESI高被引论文在榜: 0 展开所有

万方被引频次:

中文被引频次:

近30日浏览量: 2

在线人数/总访问数:283/4297499
地址:北京工业大学图书馆(北京市朝阳区平乐园100号 邮编:100124) 联系我们:010-67392185