摘要:
By taking into account of the factors including CFG composite foundation, train load, backfill grouting, grouting pressure, shield tunnel working face pressure of soil compaitinent, the numerical model of FLAC3D is established in terms of the geological and hydrogeological conditions, and the whole process of the shield tunnel traversing beneath a high-speed railway's subgrade is simulated, thus the lateral and longitudinal settlement of the subgrade surface was predicted. The results show that the maximum settlement on the subgrade surface amounts to 6.88 mm, and the maximum settlement grade is 0.29 parts per thousand, and settlement trough with unimodal shape is comparatively flat; the longitudinal settlement induced by excavation of the twin shield tunnels consists of 6 stages, and the maximum longitudinal settlement grade equals to 0.27 parts per thousand.