Zhang, M. (Zhang, M..) | Zhang, Z. (Zhang, Z..) | Chen, F. (Chen, F..)

Indexed by:

Scopus PKU CSCD

Abstract:

A variety of construction problems, such as bad cutting effects of cutters, unreasonable boring parame- ters and blowout, are often encountered during shield tunnelling under unfavorable geological conditions. Aimed at these construction difficulties of high pressure, abundant underground water, fractured rock stratum, long distance and small-radius curves of Fuzhou metro, the mechanical behaviors of cutting tools were analyzed through theoreti- cal calculations of cutter cutting force, then the reasonable cutter configuration, tunneling parameters and the proper time for cutter replacement were presented. Some measures, such as screw conveyor renovation, mucking control and lowering of groundwater, were adopted for controlling blowout based on practice. The stability of excavation face was analyzed by numerical simulation, and the measures for shield boring and posture control in the long distance and small radius curved tunnels were summarized. The conclusions are as follows: 1) when shield machine is driven in fractured stratum, the effect of lateral impact force produced by spalling rock on cutter will be very large and rein- forcement is needed for cutter; 2) cutter replacement should be taken at proper time based on muck samples in con- ditions of increasing of total shield thrust by 4 000-7 000 kN, cutter torque by 1 000-1 500 kN•m and driving speed smaller than 10 mm/min; 3) adopting screw conveyor device with innovative anti-blowout devices and control measures for ground precipitation and mucking, it controls blowout effectively; 4) the maximum axis offset and the height offset of segment meet the requirements of shield construction specifications during shield construction of long distance small-radius curved tunnel. © 2018, Editorial Office of "Modern Tunnelling Technology". All right reserved.

Keyword:

Blowout; Configuration of cutting tools; conveyor; curved tunnel; Driving parameters; Fractured stratum; High-pressure and abundant underground water; Innovation of screw; Replacement of cutting tools; Shield machine; Small-radius

Author Community:

  • [ 1 ] [Zhang, M.]Beijing Collaborative Innovation Center for Metropolitan Transportation, Beijing University of Technology, Beijing, 100124, China
  • [ 2 ] [Zhang, Z.]Beijing Collaborative Innovation Center for Metropolitan Transportation, Beijing University of Technology, Beijing, 100124, China
  • [ 3 ] [Chen, F.]The 6th Engineering Co.Ltd. Of China Railway 17th Bureau Group Co.Ltd, Fuzhou, 350014, China

Reprint Author's Address:

  • [Zhang, Z.]Beijing Collaborative Innovation Center for Metropolitan Transportation, Beijing University of TechnologyChina

Show more details

Related Keywords:

Related Article:

Source :

Modern Tunnelling Technology

ISSN: 1009-6582

Year: 2018

Issue: 6

Volume: 55

Page: 197-203 and 209

Cited Count:

WoS CC Cited Count: 0

SCOPUS Cited Count: 3

ESI Highly Cited Papers on the List: 0 Unfold All

WanFang Cited Count:

Chinese Cited Count:

30 Days PV: 0

Online/Total:825/5612109
Address:BJUT Library(100 Pingleyuan,Chaoyang District,Beijing 100124, China Post Code:100124) Contact Us:010-67392185
Copyright:BJUT Library Technical Support:Beijing Aegean Software Co., Ltd.