Han, X.-Y. (Han, X.-Y..) | Zhang, S.-J. (Zhang, S.-J..) | Gan, Y.-P. (Gan, Y.-P..) | Wang, H.-C. (Wang, H.-C..) | Peng, Y.-Z. (Peng, Y.-Z..) (学者:彭永臻)

收录:

Scopus PKU CSCD

摘要:

In order to treat the digested sludge dewatering liquor bypass and reduce influent ALR of wastewater treatment plant, the startup and maintenance of nitritation was investigated in an A/O reactor. NOB activity was inhibited and nitritation was stated up successfully by increasing the influent ALR (in N, the same below) step by step from 0.23 kg/(m3·d) to 0.78 kg/(m3·d), in spite of normal temperature, long SRT and high DO concentration. Due to the deficiency of alkalinity in influent, nitritation could be maintained steadily by the associated inhibition of free ammonia (FA) and free nitrous acid (FNA). The nitrite accumulation ratio always kept at above 90% during the period of maintaining nitritation for 30 days, and correspondingly the average concentration of DO was higher than 2 mg/L. The nitrite accumulation ratio did not decline even if the average DO concentration increased to 4.8 mg/L, which demonstrated that high DO could not destroy the nitritation built by the associated inhibition of FA and FNA. The concentration of FNA at the last chambers was increased by reducing the influent ALR in order to enhance the inhibition of FNA. The nitritation was still maintained for two months although the inhibition of FA was weakened. But the nitritation was destroyed completely in 3 days after the inhibition of FNA was eliminated, which showed the inhibition of FNA to NOB was very critical to maintain steadily nitritation.

关键词:

Biological nitrogen removal; Free ammonia (FA); Free nitrous acid (FNA); Nitritation; Sludge dewatering liquor

作者机构:

  • [ 1 ] [Han, X.-Y.]Key Laboratory of Beijing for Water Quality Science and Water Environmental Recovery Engineering, Beijing University of Technology, Beijing 100124, China
  • [ 2 ] [Han, X.-Y.]China BCEL International Engineering Co. Ltd., Beijing 100026, China
  • [ 3 ] [Zhang, S.-J.]Key Laboratory of Beijing for Water Quality Science and Water Environmental Recovery Engineering, Beijing University of Technology, Beijing 100124, China
  • [ 4 ] [Zhang, S.-J.]Beijing Drainage Group Co. Ltd., Beijing 100063, China
  • [ 5 ] [Gan, Y.-P.]Beijing Drainage Group Co. Ltd., Beijing 100063, China
  • [ 6 ] [Wang, H.-C.]Beijing Drainage Group Co. Ltd., Beijing 100063, China
  • [ 7 ] [Peng, Y.-Z.]Key Laboratory of Beijing for Water Quality Science and Water Environmental Recovery Engineering, Beijing University of Technology, Beijing 100124, China

通讯作者信息:

  • 彭永臻

    [Peng, Y.-Z.]Key Laboratory of Beijing for Water Quality Science and Water Environmental Recovery Engineering, Beijing University of Technology, Beijing 100124, China

电子邮件地址:

查看成果更多字段

相关关键词:

相关文章:

来源 :

Environmental Science

ISSN: 0250-3301

年份: 2009

期: 3

卷: 30

页码: 809-814

被引次数:

WoS核心集被引频次: 0

SCOPUS被引频次:

ESI高被引论文在榜: 0 展开所有

万方被引频次:

中文被引频次:

近30日浏览量: 1

在线人数/总访问数:1519/4278494
地址:北京工业大学图书馆(北京市朝阳区平乐园100号 邮编:100124) 联系我们:010-67392185
版权所有:北京工业大学图书馆 站点建设与维护:北京爱琴海乐之技术有限公司